Temporary Removal Procedures

Below is the sequence of action that must occur in the temporary removal of the lockout/tagout devices:

Be sure to follow LOTO procedures for temporary testing.
  1. The machine or equipment must be cleared of tools and materials.
  2. Workers must be removed from the machine or equipment area.
  3. All lockout or tagout devices may then be removed.
  4. Authorized workers may then proceed to energize and test or position the equipment or machinery.
  5. Following testing or positioning, all systems must be de-energized and energy control measures reapplied to continue the servicing and /or maintenance.

Knowledge Check Choose the best answer for the question.

7-4. During lockout/tagout, which of the following actions should occur before authorized workers proceed to energize and test or position equipment or machinery?