Temporary Removal Procedures
Below is the sequence of action that must occur in the temporary removal of the lockout/tagout devices:
- The machine or equipment must be cleared of tools and materials.
- Workers must be removed from the machine or equipment area.
- All lockout or tagout devices may then be removed.
- Authorized workers may then proceed to energize and test or position the equipment or machinery.
- Following testing or positioning, all systems must be de-energized and energy control measures reapplied to continue the servicing and /or maintenance.
Knowledge Check Choose the best answer for the question.
7-4. During lockout/tagout, which of the following actions should occur before authorized workers proceed to energize and test or position equipment or machinery?
You forgot to answer the question!