Emergency Shutdown System
When well-completion operations are conducted on a platform where there are other hydrocarbon-producing wells or other hydrocarbon flow, an emergency shutdown system (ESD) manually controlled station should be installed near the driller's console or well-servicing unit operator's work station.
When well-work over operations are conducted on a well with the tree removed, an emergency shutdown system (ESD) manually controlled station should be installed near the driller's console or well-servicing unit operator's work station, except when there is no other hydrocarbon-producing well or other hydrocarbon flow on the platform.
Knowledge Check Choose the best answer for the question.
5-2. When well-completion operations are conducted on a platform where should an emergency shutdown system (ESD) station be installed?
You forgot to answer the question!