Demolition by Deliberate Collapse

Another method of demolishing a building, chimney or stack is by deliberate collapse.

Demolition in Germany

Deliberate collapse requires extensive planning and experienced personnel, and should be used only when conditions are favorable.

  • There must be a clear space for the fall of the structure of at least 45 degrees on each side of the intended fall line and 1½ times the total height of the chimney.
  • Considerable vibration may occur when the chimney falls, so there should be no sewers or underground services on the line of the fall.
  • Post lookouts on the site and arrange for warning signals.
  • Keep the public and other workers at the job site well back from the fall area.

Knowledge Check Choose the best answer for the question.

5-5. What should you do when deliberately collapsing a building?