32-6. Activity Hazard Analysis (AHA) Requirements.
Development of AHAs
- Develop AHAs in compliance with either paragraphs 1-6 or 2-6, specifically for airfield operations.
- The AHA must detail work methods, including the utilization of systems, equipment, materials, tools, and Personal Protective Equipment (PPE).
- Ensure the AHA outlines controls to mitigate or manage hazards to an acceptable level.
32-7. Minimum Plan Requirements.
CSPP and SPCD Notification and Approval Process
- The USACE supervisor/KO or COR must notify the appropriate FAA Regional or District Office about the construction and provide them with a copy of the Construction Safety and Phasing Plan (CSPP) or Safety Plan Compliance Document (SPCD).
- Before any changes to the approved CSPP or SPCD are made, the USACE supervisor/KO or COR and the Airfield Manager must be informed in writing of the proposed revisions.
Construction Safety and Phasing Plan (CSPP)
- A Competent Person (CP) must prepare the CSPP in accordance with FAA 150/5370-2F and UFC 3-260-01, following the format specified in FAA 150/5370-2F.
Safety Plan Compliance Document (SPCD)
- A CP must prepare the SPCD in accordance with FAA 150/5370-2G and UFC 3-260-01, following the format specified in FAA 150/5370-2G.
Knowledge Check Choose the best answer for the question.
32-3. Before any changes to the approved CSPP or SPCD are made, who must be informed in writing of the proposed revisions?
You forgot to answer the question!