Criteria for MOC (Continued)

Management of change procedures do not apply to situations involving replacement in kind (such as, replacement of one component by another component with the same performance capabilities).

group of employees sitting around a conference table
BSEE issuing a possible incident of noncompliance.

You should review all changes prior to their implementation.

The following items should be included in the management of change procedures:

  • the technical basis for the change
  • impact of the change on safety, health, and the coastal and marine environments
  • necessary time period to implement the change
  • management approval procedures for the change
  • employees, including contractors whose job tasks will be affected by a change in the operation, should be informed of, and trained in, the change prior to startup of the process or affected part of the operation
  • If a management of change results in a change in the operating procedures of the SEMS program, such changes should be documented and dated.

Knowledge Check Choose the best answer for the question.

3-2. Management of change procedures do not apply to situations involving _____.