15.C Multiple Lift Rigging (MLR) ("Christmas Tree Rigging").
USACE allows multiple lift rigging practices for the purpose of erecting/placing structural steel ONLY.
15.C.01 Strict compliance with this section and 29 CFR 1926.753 Subpart R must be mandated.
15.C.02 A lift using a MLR Assembly is considered a critical lift. It requires a carefully detailed, written critical lift plan per Section 16.H. In addition, all details and requirements of this section are required to be addressed:
- Identifying all multi-lift hazards on the job site;
- Beam list;
- Determining load capacity;
- Determining weight of a member;
- Proper crane hand signals;
- Safety rules for MLR;
- Seven-foot rule;
- Safe route/path of load and crane;
- Power line issues;
- Crane requirements;
- Marking centerlines;
- Use of tag line;
- Qualifications and/or certifications of the operator(s) and rigger(s) to be performing these operations;
- Rigging equipment: wire rope slings, hooks & shackles;
- Clean lay-down area;
- Cribbing;
- Storage/staging;
- Wind/environmental limits; and
- Personal protective equipment.
15.C.03 A lift using a MLR Assembly may only be performed if the following criteria are met:
- A MLR assembly is used;
- A maximum of five members are hoisted per lift;
- Only beams and similar structural members are lifted;
- All employees engaged in MLR must be trained in the following:
- (1) The nature of the hazards associated with multiple lifts;
- (2) The proper procedures and equipment to perform multiple lifts required in this section and as per 29 CFR 1926.753(e).
- All loads must be rigged by a QR per Section 15.B;
- No crane is permitted to be used for multiple lift where such use is contrary to the manufacturer's specifications and limitations;
- Components of the MLR assembly must be specifically designed and assembled with a maximum capacity for total assembly and for each individual attachment point. This capacity, certified by the manufacturer or a QR, must be based on the manufacturer's specifications with a 5:1 safety factor for all components.
- The total load must not exceed:
- (1) The working load limit (WLL) of the hoisting equipment specified in the hoisting equipment load charts;
- (2) The rigging capacity specified in the rigging rating chart.
- The MLR assembly must be rigged with members:
- (1) Attached at their center of gravity and maintained reasonably level;
- (2) Rigged from the top down; and
- (3) Rigged at least 7 ft (2.1 m) apart.
- The members on the MLR assembly must be set from the bottom up.
- Controlled load-lowering must be used whenever the load is over the connectors.
Knowledge Check Choose the best answer for the question.
15-3. What is the lift capacity safety factor for a Multiple Lift Rigging (MLR) assembly?
You forgot to answer the question!