14-5. Inspection Requirements.
Debris Netting Assessment and Selection
- Assess and document the size, weight, and potential fall height of debris.
- Select debris netting with appropriate mesh size and strength to contain the expected debris without penetration.
- Ensure the debris netting is properly supported to handle the anticipated load.
14-6. Activity Hazard Analysis (AHA) Requirements.
Develop AHAs according to paragraphs 1-6 or 2-6, as applicable.
14-7. Minimum Plan Requirements.
Not Applicable.
Knowledge Check Choose the best answer for the question.
14-3. Debris netting must be properly supported to _____.
You forgot to answer the question!