Load Path Welds
This inspection will visually ensure that load path welds are not damaged.
Develop a systematic plan with the crew to conduct a focused visual inspection of the load path. Additional light and tools for scraping and brushing the welds should be available.
The inspection plan should address access to the area, necessary fall protection, and in some cases energy isolation and lockouts. Rig operations may need to be stopped or modified to ensure the safety of the inspector.
Rig Components
For each major rig component of the load path, note any: weld damage, bent structures, corrosion, cuts or holes, modifications, fluid build-up, and freeze damage. Specific instructions for each component are below.
Knowledge Check Choose the best answer for the question.
11-10. Why may rig operations need to be stopped or modified during weld safety inspections?
You forgot to answer the question!