6-8. General Requirements.

Asbestos and Lead Hazard Control

  • Do not use or bring known friable Asbestos Containing Materials (ACMs) onto USACE projects.
  • Evaluate construction or maintenance projects for potential contact with ACM, and develop an Asbestos Management Plan if there's potential for disturbance.
  • Label all ACMs and provide a site map indicating the location of asbestos hazards if labeling is not possible.

Lead Hazard Control

  • Use lead-based paints only with prior written approval and never inside residences or medical facilities.
  • Evaluate projects for potential occupational lead hazard exposure and develop a written Lead Compliance Plan if exposure is likely.
  • Label all lead sources that may generate occupational exposure, or provide a site map indicating the location of lead hazards if labeling is not feasible.

Protection from Hot Substances

  • Ensure Personal Protective Equipment (PPE) is evaluated for efficiency in hot atmospheres and protects from heat and chemical hazards.
  • Consider heat stress precautions and relocate ventilation intake air vents away from where hot substances are heated.
  • Do not carry hot substances up or down ladders and ensure containers for transporting hot substances are of substantial construction.

Protection from Harmful Plants, Animals, and Insects

  • Wear appropriate PPE, treat clothing with DEET or Permethrin, and drain or spray insect breeding areas.
  • In areas with exposure to venomous snakes or lizards, ensure PPE such as snake chaps or knee-high snake boots are worn.
  • For exposure to poisonous plants, remove or destroy plants where practicable, provide appropriate protective clothing, and ensure soap and water are available for washing.

Knowledge Check Choose the best answer for the question.

6-9. An Asbestos Management Plan should be developed on construction or maintenance projects for potential contact with ACM if _____.

6-8. General Requirements (f.–i.).