2-5. Inspection Requirements.
External Agency Inspections
- Immediately inform the KO, COR, and local SOHO about any OSHA or other regulatory agency inspections. Allow them to join the inspection without delay.
- Provide copies of any citations, reports from the inspector, and corrective action responses to the KO, COR, and local SOHO.
- The local SOHO must share these documents and corrective actions with division and HQUSACE-SO.
Contractor SOH Inspections
- The APP requires frequent safety inspections and audits by the QC and SSHO, ensuring compliance with the APP and manual, documented in a written log.
- Inspections of the work sites, material, and equipment to ensure compliance with the APP and this manual must be conducted at least daily by the SSHO and QC.
- The SSHO must maintain a deficiency tracking system to list and monitor unresolved deficiencies until they are addressed as per paragraph 2-8.f(3).
Knowledge Check Choose the best answer for the question.
2-4. Inspections of the work sites, material, and equipment to ensure compliance with the APP and EM 385-1-1 must be conducted by the SSHO and QC _____.