16-8. General Requirements.

Operation of Lifting and Hoisting Equipment (LHE)

  • Operators must keep the manufacturer's operating manual, load-rating chart, and crane logbook in the equipment's cab at all times.
  • Modifications or additions affecting LHE capacity or safety require the manufacturer's written approval and appropriate updates to instruction plates, tags, or decals.
  • Hoisting wire ropes must be installed according to ANSI/ASME standards and the manufacturer's instructions, ensuring at least two full wraps on the drums.

Communications during LHE Operations

  • Operators must use a standard signal system and have a signal person when the operator's line of sight is obstructed or when deemed necessary.
  • Only one person may communicate with the operator at a time, except for emergency stop signals, which anyone can issue, and the operator must obey immediately.

General Safety Practices

  • Avoid riding on hoisting equipment not meant for personnel and use tag lines to control loads unless impractical or hazardous.
  • Cease operations during a slack line condition to check rope seating and maintain a safe distance from power lines, following specific safety measures.
  • The employer must ensure physical clearances are maintained around the LHE and use crane mats for a stable work surface when required.

Environmental Considerations for LHE Operation

  • Do not operate LHE in wind speeds exceeding the manufacturer's recommendations, and cease operations in adverse weather conditions like icing, reduced visibility, or lightning proximity.
  • Plan work activities according to weather forecasts, be prepared to stop operations during bad weather, and ensure night operations are adequately illuminated.

Knowledge Check Choose the best answer for the question.

16-12. Modifications or additions affecting LHE capacity or safety require the _____.

16-8. General Requirements. (v.–w.).