16-6. Activity Hazard Analysis (AHA) Requirements.
Activity Hazard Analyses (AHAs) Development
- Develop AHAs as per the specified paragraphs, ensuring documentation of crane operator certifications and qualifications before starting specific activities or tasks.
Boom Assembly and Disassembly
- Include boom assembly and disassembly operations in the AHA and identify the associated Control Points (CPs).
Portal, Tower, and Pillar Cranes
- Before assembly or disassembly, establish work procedures in the AHA, taking into account site-specific needs, including crane location, foundation design, and clearances.
Hoisting with Hydraulic Excavating Equipment
- Prepare a hoisting operation specific AHA, documenting operator qualifications, operational testing, and specific conditions for equipment operation.
- Ensure adherence to proper operating procedures, including the use of manufacturer's load rating charts, rigging inspection, and use of tag lines.
- Maintain adequate communication and ensure the stability of surfaces beneath the hydraulic excavating equipment.