28-4. Roles and Responsibilities.
Controlling Contractor Duties
- The Controlling Contractor must develop the sequence of erection activities.
- The Controlling Contractor must provide written notifications as specified.
- The Controlling Contractor must ensure proper site layout and coordinate other construction processes.
Competent Person (CP) Responsibilities
- The CP must evaluate bracing equipment and the need for guying or bracing on columns.
- The CP must determine bolting requirements.
Qualified Person (QP) Obligations
- The QP must provide all necessary training and prepare steel erection plans.
- The QP must direct the use of shim packs and design alternate means of stabilizing joists.
- The QP must approve the use of certain materials for fall arrest anchorage.
Structural Engineer of Record Responsibilities
- The Structural Engineer must approve all repairs or modifications to anchor rods or bolts and specify bolt tightness.
- The Structural Engineer must approve all modifications to joists and girders.
28-5. Inspection Requirements.
Not Applicable.
28-6. Activity Hazard Analysis (AHA) Requirements.
Develop AHAs according to paragraphs 1-6 or 2-6, as applicable.